FM 110 16” Waterline Installation

Project Type:
Utility
Project Status: 
In Construction
Location: 
Yarrington Road
Kyle, TX 78640

This project includes the installation of approximately 5,000’ of 16” PVC waterline from the Yarrington Pump Station, along the new FM 110, and ultimately connecting to the future Waterstone Subdivision. The project is currently in 100% design and will go into construction later this year.

FM110 Waterline Map
FM 110 Waterline
Status Updates

As of 6/14/24:

Contractor working on finishing grade and seeding along FM 110.

Contractor finishing all items noted in Final Walkthrough.

Project to be completed within the next two weeks.