FM 1626 Ground Storage Tank & Pump Station
Project Type:
Road / Sidewalk
Project Status:
In Construction
The City of Kyle has awarded a contract to Archer Western to construct one of two Alliance Water take-points. Construction activities on-site have begun, beginning with the construction of a 3.5 million ground storage tank. Additional improvements will include an additional pump station, meter station, and associated equipment.
![FM 1626 Lift Station FM 1626 Lift Station](https://www.cityofkyle.com/sites/default/files/imageattachments/public_works/project/21437/fm1626.jpg)
![FM 1626 Lift Station FM 1626 Lift Station](https://www.cityofkyle.com/sites/default/files/imageattachments/public_works/project/21437/fm_1626_lift_station.png)
Status Updates
As of 7/2/24:
- Geotechnical testing of 24 of 28 lifts completed.
- Archer Western are continuing to extend their work schedule to 7am-7pm, Monday-Friday and on Saturday 8am-3pm.
- Inspector and City of Kyle Project Manager trailer on site pending electrical hookup by next week.
- Assembly of undergroundpipe completion is currently undergoing pressure testing before being installed.