Viking Construction will be microsurfacing roads to improve the appearance & life of the road beginning Oct. 5 and going through Oct. 15. Please see the construction schedule below

Only Kyle Crossing, McNaughton & New Bridge Drive will have thru traffic during repairs. All other streets will be completely closed for traffic. 

All vehicles along the affected stretches of road must move vehicles before 8 a.m. the day of construction. Please plan accordingly.
 

Microsurface road project dates:

  • Monday, October 5, 2020:
    • Autumn Sage Parkway - between Camelia Parkway & FM 150
    • 10/05 - Amber Oak Drive - between Amberwood Loop & Cherrywood
  • Tuesday, October 6, 2020:
    • Musgrav - between Stennis & Enterprise
    • Steeplechase Boulevard - between Goforth Road & Brandi Circle
    • Lox - between FM 150 & Stennis
  • Wednesday, October 7, 2020:
    • Mather Road - between Se Corner & Hartson
    • Kyle Crossing - between Old Bridge Trail & Kohlers Circle
  • Thursday, October 8, 2020
    • Mather Road - between Negley & Hartson
    • Stennis - between Atlantis & Goddard
  • Friday, October 9, 2020:
    • Mather Road - between McNaughton & SE Corner
    • Hawthorn Drive - between Hometown Parkway & FM 150
    • Enterprise - between Musgrav & Old Post Road
  • Monday, October 12, 2020 
    • Cherrywood - between Amberwood loop & Windy Hill Road
  • Tuesday, October 13, 2020:
    • New Bridge Drive - between FM 150 and Holly Grove Street
  • Wednesday, October 14:
    •  McNaughton - between Fairway & Mather Road
  • Thursday, October 15, 2020
    • Sandars Lane - between Fairway & Kohlers Crossing
    • 10/15 - Kyle Crossing - between Old Bridge Trail & Kohlers Crossing 

This schedule could be adjusted based on weather and other unforeseen reasons. For more information, call 512- 262-1010.